Client: Cardinal Logistics
Construction: Haydn & Rollett
Works Completed: Full underslab power + data ducting installation
Timeframe: 12 weeks
For stage two of the Cardinal Logistics Drury project, we were contracted to install the complex underslab power and data ducting system. With various aspects of the project happening simultaneously—earthworks, foundation laying, drainage installation, floor preparation—coordinating the efforts of different teams was essential. Effective communication and project management were key to keeping everything on track.
Working alongside the main and sub-contractor teams, we:
The project was completed within the timeframe and budget, with zero rework required thanks to precise execution and clear communication throughout. By providing comprehensive as-builts, we removed future guesswork and set the client up with a streamlined foundation for ongoing site maintenance and upgrades.